120 MW Mmadinare Solar Plant Reaches Financial Close

Botswana has reached financial close on the 120 MW Mmadinare Solar Plant, backed by USD 108 million (BWP 1.5 billion) in financing. Scatec said the close covers the second 60 MW tranche of the 120 MW development and that it is preparing to start construction on the expansion.

Total capital expenditure for the full 120 MW is estimated at USD 108 million (BWP 1.5 billion), with the engineering, procurement and construction contract value to Scatec estimated at USD 88 million (BWP 1.2 billion). Financing for the scheme consists of approximately USD 73 million (BWP 1.0 billion) of non-recourse project debt, with the balance to be provided as equity by Scatec.

Lenders named for the debt package are First National Bank of Botswana, acting through its Rand Merchant Bank division, and the International Finance Corporation. Scatec will retain 100% ownership at close and is the designated EPC contractor as well as asset manager and O&M provider, with construction and operation to be managed by Scatecs organisation.

The company said it intends to invite additional equity partners to reduce its long-term economic interest in the Solar Plant. Scatec signed a binding 25-year power purchase agreement with Botswana Power Corporation for 60 MW of output. The company estimates the Solar Plant will avoid approximately 48,000 tons of CO2 emissions per year and provide enough generation for approximately 20,000 households annually. IFC participation alongside commercial bank debt underscores continued international financing interest in bankable utility-scale solar in Botswana, which could support further deals using similar non-recourse structures.

“We mark another achievement for our renewable energy journey in Botswana as we start construction of the second phase of the project. By doubling the total capacity of the solar power plant, we demonstrate the effectiveness of our strategy, robust business model and drive to contribute to the green energy transition in Africa,” says Scatec CEO Terje Pilskog.

Project

NameMmadinare Solar Plant: Phase 2
CountryBotswana
StatusPlanning

Organizations Involved

Track every solar plant in Botswana

60 plants · 34 companies

The developer, investor, lender, offtaker and EPC on each plant, which roles are still open, and what changed this month. $89 every 3 months.

See the Botswana tracker