Guinea solar tracker
Every solar plant we track in Guinea, with the developer, investor, lender, offtaker and EPC on each, and which of those are still missing. Updated every month with what changed: new plants, new companies entering the market, and plants that moved stage.
Plants tracked
13
Plants with companies named
5
Companies active
8
Updates in the last 30 days
0
What changed in the last 30 days
0 companies new to Guinea this month. This is the part you get every month.
No updates in this period.
Who is active in Guinea
Companies named on Guinea plants, ranked by number of plants.
Developers and owners
4- VINCI Energies Guinea1 plant
- Government of Guinea (Energy Ministry) Owner1 plant
- InfraCo Africa1 plant
- +1 more
Investors and lenders
4- InfraCo Africa1 plant
- Frontier Investment Management ApS1 plant
- Government of São Tomé and Príncipe1 plant
- +1 more
Offtakers
1- Electricité de Guinée (EDG)2 plants
EPC contractors
1- Vinci Energies1 plant
Plants and who is still missing
Of 5 plants with companies named, 2 have no investor or lender named, 4 no EPC, and 3 no offtaker.
| Plant | Size | Stage | Owner | Financier | Off-taker | EPC |
|---|---|---|---|---|---|---|
| Kindia Solar Plant Last update 2026-04-22 | 50 MW Utility | Construction | VINCI Energies Guinea | Not named | Electricité de Guinée (EDG) | Vinci Energies |
| Kankan and Siguiri Solar Plant Last update 2024-09-05 | — C&I | Construction | Government of Guinea (Energy Ministry) Owner | Not named | Not named | Not named |
| Khoumagueli Solar Plant Last update 2021-05-27 | 40 MW Utility | Planning | InfraCo Africa | InfraCo Africa | Electricité de Guinée (EDG) | Not named |
| Boke Solar Plant Last update 2020-08-10 | 41 MW Utility | Planning | Not named | Not named | Not named | |
| Energy Transition and Institutional Support Programme (ETISP) Last update 2020-03-04 | — C&I | Planning | Not named | Not named |
Get the full Guinea tracker
- Every plant in Guinea, with all companies named and the roles still open.
- Every developer, investor, lender, offtaker and EPC active in the market.
- Each month: new plants, companies new to Guinea, and plants that moved stage.
- $89 every 3 months. Cancel anytime; access runs to the end of the paid period.
Access opens as soon as you've paid. Not ready? The free newsletter sends the main updates every two weeks.